Task update not fully working

Need help with VueMinder Pro or Ultimate? Ask your questions here.
Andreas
Posts: 2
Joined: Thu Jan 18, 2018 10:03 am

Task update not fully working

Post by Andreas » Thu Jan 18, 2018 10:14 am

I have a problem when one of two users create a task and end it the other one finished it the graphic doesnt update but the text does. If the other user create one task and end it both the text and graphic (greyed out) follows on to the other without problem. This is done on Mysql connections. Seems like a bug since the text that it has finished is transfered without problem but not the "greyout" on the task.
Both users has full permission on task.
But one user that was not the original owner can create a task and finish it (greyout) and the other one will se it greyout.
Do you have a solution before I buy the program or is it a bug?

With regards Andreas

User avatar
VueSoft
Dan Chartrand
Posts: 3853
Joined: Sat Aug 23, 2008 12:39 am
Location: St. Louis, Missouri, USA
Contact:

Re: Task update not fully working

Post by VueSoft » Thu Jan 18, 2018 11:35 pm

Hi Andreas, welcome to the forums. Please open the Sharing Options on both computers and make sure the boxes labeled "Share event completion status" and "Share calendar and event appearances" are checked. Also, under the "View -> Color Events Using" menu, make sure both computers are set to "Calendar Color". Does that fix it?
Dan Chartrand, Founder
VueSoft LLC | St. Louis, Missouri, USA

Andreas
Posts: 2
Joined: Thu Jan 18, 2018 10:03 am

Re: Task update not fully working

Post by Andreas » Fri Jan 19, 2018 9:55 am

That was the problem! Thank you for the help!